Joint Technical Input on Temporary Capacity Restrictions

Together with other infrastructure managers, railway undertakings, multimodal transport operators and sector associations we issued a Joint Technical Input on Temporary Capacity Restrictions. We propose a better way to manage traffic affected by temporary capacity restrictions and track works.

The resulting proposal to be submitted to the European Commission as technical input, is built around three key concepts:

Railway track closed for works

Preliminary Phase

In which infrastructure managers, railway undertakings and multi-transport operators work together to develop the most appropriate traffic solution. The goal is to offer better-quality alternative paths.

Timetable Slices

Designed to process all TCR-related impacts on timetables from origin to destination within a pre-defined rescheduling window and applying common European deadlines. This should significantly reduce repeated adjustments and workload for infrastructure managers, railway undertakings and multi-transport operators.

Frozen Period

Enabling planning stability for all involved stakeholders and thereby improving the reliability of rail services for customers in passenger and freight traffics.